900 MW
Tuckahoe Technology Park
(West of Route 288, bordered by Hockett Road and Patterson Avenue)
Details: Developer Tract (via VALCO Goochland, LLC) is planning a 900 MW data center campus called the Tuckahoe Technology Park in Goochland's Technology Overlay District (TOD). It spans 872 acres bordered by Hockett Road, Route 288, and Patterson Avenue. This particular area in the district is commonly referred to as "TOD West" and is zoned as Conditional Use Permit (CUP), meaning it requires public hearings and approval by local Goochland officials.
The campus features 12 buildings and 3 substations. Buildings are capped at 60 feet, allowing up to 80 feet if given a 500-foot residential buffer. The campus could have approximately 300 diesel generators.
Status: Pre-applications were submitted in June 2026, followed by a formal permit application filed in August 2026. The application is currently going through community meetings and formal public hearings before the Goochland Planning Commission and the Board of Supervisors.
Tuckahoe Technology Park website
600 MW
The Rockville/H2 facility
(North of West Broad Street, near the intersection of Ashland Road and I-64)
Details: Rockville LLC and H2 LLC control 151 acres off Ashland Road located within Goochland's Technology Overlay District (TOD). The landowners testified they discussed a 600 MW data center campus with a developer. The proposal featured three large-scale buildings north of West Broad Street, at the corner of Ashland Rd and I-64. The land is zoned as by-right.
Status: Conceptual interest submitted during Dominion's transmission line route proposals.
200 MW
The West Creek Industrial facility
(East of Route 288 and north of Patterson Avenue at the old Tuckahoe Emergency Center site)
Details: Western Industrial/West Creek Industrial submitted a request to Dominion Energy for a 200 MW data center development at the former Tuckahoe Creek emergency room site located within Goochland's Technology Overlay District (TOD). The project requires constructing one new substation to supply power to the site. The land is zoned as by-right.
Status: The ELOA has been requested but not executed.